JW Marriott DC Diner, Q-SYS programming. Tick each step as you finish it. Your ticks save on this phone only.
· Built from playbook.md + open-questions.md (11/11/2026).
JW Marriott DC Diner: Q-SYS Field Programming Playbook
For: Lorenzo Snead (Phoenix Technologies), on site at the rack, 1331 Pennsylvania Ave NW
Prepared: Wed 11/11/2026 (PT) by Superior Connects ops.
Sources: Superior "JW Diner Q-SYS Design Plan 2026-11-09" (the Plan), EMD/W-T "JWDC AV Programming Spec 2.4" (the Spec), Creation Networks order emails, and the official Q-SYS docs linked in each step.
Rules for this page
0 Quick read: the 3 Cores (decide this first)
Hardware on order: 3x Core 8 Flex (CN8699), 1x QIO-ML4i, 1x QIO-L4o, QIO-IR1x4 (confirm on site whether it is present), TSC-50-G3 touch screens (count the TSC panels installed: plan shows 4, orders show 5), 3x Lab Gruppen E 5:4, 5x RDL DD-BN31 Dante plates, 1+ Netgear M4250-26G4F-PoE+, and 1 iPad Air.
Recommendation (simplest valid setup): ONE design on ONE Core.
Why not 3 separate Cores, one per zone? It would be valid Q-SYS, but it's the wrong fit here:
Why not a redundant pair today? Core 8 Flex does support Core redundancy (set Is Redundant = Yes and name the Backup Core). However, Flex outputs cannot be wired redundantly, both Cores must be online during install, and the Core Redundancy network service has to be enabled on both. (Core Redundancy) That's extra complexity we don't need to get sound working today. Revisit only if EMD or Dana asks for it.
How to tell which mode each unit is in:
A Before you start (10-minute checklist)
Open questions (JWDC Diner Q-SYS: Questions only Lorenzo can answer on site)
From open-questions.md. Tick each once you have the answer; these ticks don't count toward progress.
Type your answers and send them (section J)(Ask these first. Each answer changes a step in playbook.md.)
1. What exactly is failing? (pick the step)
2. Versions
3. The 3 Core 8 Flex units
4. Speakers and amps
5. Inputs and sources
6. Touch screens, iPad, IR
7. Network
8. Fire alarm
9. Still TBD in our Plan (not Lorenzo's problem today)
B Find the hardware (Configurator + Core Manager)
C Build the design (this job)
Build the full 3-zone design now and enable Phase 1 speakers only. Pre-build the Phase 2 chains (including AMP-3) and keep the Phase 2 UCI controls hidden or disabled (Plan §1.2 / §8).
Zones (Proposal §2.1): Diner & Bar (16 spk design), Private Dining (4), Restaurant & Lounge (33).
Which zones the 18–20 installed Phase 1 speakers serve is TBD (Plan §1.2). Ask yourself first, and do not assume 16+4=20.
C1. Inventory
C2. Schematic per zone (repeat x3)
Make one schematic page per zone (left pane Schematic Pages). Components come from the Schematic Library on the right; use its search box. Connect output pins to input pins by dragging wires. Use Signal Names to link between pages (Getting Started).
Chain per zone (Plan §7):
C3. Fire-alarm input to system mute
Per the Q-SYS KB (Fire Alarm Relay with Digital TTL) and GPIO In (Core 8 Flex):
C4. Master on/off and 4:00 AM reset (Spec 2.4.A.3.3 and .11)
C5. QIO-IR1x4 (only if it's on site)
C6. Check it
D UCIs (touch screens + iPad)
E Deploy, test, and back up
F Test & commission (per zone, against Spec 2.4)
Run all of this per zone: Diner & Bar / Private Dining / Restaurant & Lounge. Phase 2 zones: only the UCI behavior can be checked.
G Troubleshooting
H Escalation (call early; it's free)
I Q-SYS Training pages (read only what you need)
These are Q-SYS Training pages, not videos. Some may need a free Q-SYS account sign-in.
J Answer these on site
Don't enter passwords or logins here.
Tapping Send answers emails everything below (and your photos) to Superior Connects at info@superiorconnects.com through FormSubmit. Your typing is also saved on this phone until you clear it.